Finally
the
following project sites and activities were picked and shall be executed under the
program:
- Construction
of about 200 new classrooms including
appropriate sanitation facilities. e.g. Latrines and about 40 ancillary
rooms.
- Rehabilitation
of about 200 classrooms that
are not or partly functional.
- Provision
for adequate Furniture and Teaching
Material.
-
Connection of schools to the urban Supply Networks, whenever technically
feasible and financially viable
(Water, Electricity
etc.)
- Teacher
Training on
counseling skills, teaching methods and HIV/AIDS prevention.
- Development
of Maintenance Strategies for the promoted schools.
| No |
Primary School |
Rehabilitation Classrooms |
New
Construction Classrooms |
Total Classrooms |
| 1 |
Mathare4a |
12 |
23 |
35 |
| 2 |
Mukuru Kayaba |
0 |
24 |
24 |
| 3 |
St.Elizabeth |
0 |
40 |
40 |
| 4 |
Baba Dogo |
0 |
600 m of Boundary Wall |
0 |
| 5 |
James Gichuru |
31 |
3 |
34 |
| 6 |
Wangu |
33 |
3 |
36 |
| 7 |
New Kihumbini |
0 |
8 |
8 |
| 8 |
Kinyanju Road |
11 |
24 |
35 |
| 9 |
Ngei |
4 |
32 |
36 |
|
|
91 |
154 |
245 |
Key
|
Complete |
|
Under Construction |
|
Tender Phase |
|
shiftet to Phase II |
.JPG)